Plan of Actions and Timeline
-
Start:
January 2025
March/April 2025:
Conceptual drawings done
2025
January 2025:
Update alley appraisal (will be ready in early March), Hiring architect
September 2025:
Submit entitlement package prepared by architect
- First half of 2026: Entitlement approval
2026
First half of 2026 - First half of 2027:
Schematic Design, Design Drawings,
Construction documents prepared
by architects and engineers
Apply for utility connection early on.
- First half of 2027 -
Second half of 2027:
Plan check (est. 6 months)
Second half of 2027
Construction start
2027
- 2028
- 2029
Second half of 2029:
Construction finish,
Leasing start